| Comparison to conventional method |
|
Time and labour The Bygging-Uddemann steel tank set-up allows a complete cistern to be erected with hydraulics without the need of expensive construction cranes and with the minimum amount of labour. |
|
1 Nos typical tank
|
|
||||
| BYUM method | Conv.method | ||||
| Construction time | 14 weeks (76%) |
17 weeks (100%) |
|||
| Manpower |
7300 hours (56%) |
12.900 hours (100%) |
|||
|
Construction time and manpower based on European standard 40 hours/week |
|||||